What it is

A decision-support framework, not a single model, for resolving instream flow problems by comparing the habitat and other consequences of alternative flow regimes and negotiating a solution. It links hydrology, habitat (usually via PHABSIM or another habitat model), water quality and temperature models, and runs through five phases from problem identification to problem resolution.

How it works

  1. Problem identification: legal-institutional analysis of parties and decision process, and physical analysis of affected reaches, resources and baseline and project flow series
  2. Study planning: agree on the information, scales, variables and methods needed
  3. Study implementation: collect data and build hydraulic, habitat (e.g., PHABSIM), temperature and water-quality models
  4. Alternatives analysis: compare habitat time series and other outcomes of each alternative with the baseline for effectiveness, feasibility, risk and economics
  5. Problem resolution: negotiate a solution and continue learning after the project.

What you get

Output
Scenarios of outcomes; Habitat-flow curves
Kind of answer
Compares options: it sets out how the river responds to flow, so scenarios can be compared and negotiated.

What it needs

Data needs
High
Effort
Multi-year / expert panel
Resolution
Medium to High
Typical team and time at this resolution
ItemMedium resolutionHigh resolution
Specialists2-6 people6-10 people
Environmental flow practitioners1-2 people1-2 people
Duration6-12 months6-24 months
Total effort40-140 person-days130-290 person-days

Typical figures from IFC (2018), Table 5 (p. 60), for one hydropower-project assessment, after King and Brown (2015). Estimates only: travel and stakeholder liaison are not included.

Good for, not suited to

Good for
Complex, contested or high-stakes flow decisions where several alternatives and parties must be weighed and negotiated.
Not suited to
Quick standard setting. It does not guarantee a single best answer and relies heavily on professional judgment and negotiation.

Where it came from

Origin
US Fish and Wildlife Service interdisciplinary team, USA, late 1970s-1980s (Bovee 1982; Stalnaker et al. 1995); to evaluate alternative water development and management schemes

Research on this method

Where it was defined

How to run it

Reviews, tests and criticism

Studies that apply it

Other documents cited in the register

Guidance, reports and method documents from the methods register. Most are not in the papers index.

Papers are picked from the papers index, where records are found and classified by AI from titles and abstracts. Check the paper itself before relying on it. Search the papers index for this method.

Family line

Built on it

1 method built from this one, directly or through another.

Recorded only where a document says one method is based on another; “similar to” is not counted.

About this page

Drafted with AI from the references listed (Claude, by Anthropic). A person has not checked it yet. Confirm details against the original references before relying on it.

Described from the references listed, with key statements matched by script to quoted text from saved copies. Record AM-0045, methods register v1.12. Spotted an error? hello@environmentalflows.com

All methods